Battery calculators / Runtime & backup
Understand your battery. Plan your power.
Battery Backup Size Calculator
Size nominal battery capacity for a required backup duration and a steady power demand.
Your inputs
Your result
Awaiting your inputsEnter your values and press Calculate. Your result will appear here.
The method
Formula and calculation steps
Required Ah = load W × hours × (1 + margin) ÷ (V × usable fraction × efficiency)
Work backward from the energy the load needs. The usable fraction and efficiency increase the required nameplate energy; the explicit margin is added once.
Capacity sizing does not check surge power, maximum battery current, charger compatibility or installation rules. Select equipment that satisfies those requirements separately.
Battery backup sizing for whole-home and emergency loads
A battery size calculator works backward from the required backup duration. List the critical equipment, establish its average watts, and multiply by the required hours. A whole home battery backup size calculator needs a credible load budget: backing up lights, networking and refrigeration is a different requirement from backing up heating, cooking or an entire service.
A battery bank sizing calculation gives nameplate energy and Ah, not an inverter power rating. A sump pump, car-audio amplifier or trolling motor may have surge or variable demand that is poorly represented by one continuous watt number. Measure the appropriate duty-averaged energy and separately verify the highest simultaneous power and battery current.
Continue with: Home Battery Load Planner · Solar Battery Size Calculator · UPS Battery Runtime Calculator
Worked example
A transparent starting point
100 W for 8 hours, 12 V, 80% usable, 90% efficiency and 20% margin needs 111.11 Ah.
The values below are computed with the same formula as the calculator. They are examples, not manufacturer performance claims.
How one input changes the answer
| Required backup time (h) | Required nominal capacity |
|---|---|
| 4 h | 55.55556 Ah |
| 8 h | 111.1111 Ah |
| 12 h | 166.6667 Ah |
All other inputs use the illustrative defaults in the form.
Battery backup sizing for whole-home and emergency loads — calculated examples
Each row below is calculated from the stated case inputs. Inputs not changed in a row use the assumptions listed after the table.
| Case | Changed inputs | Result |
|---|---|---|
| 100W for 4h | Required backup time: 4 h; Continuous load: 100 W | 55.55556 Ah |
| 500W for 4h | Required backup time: 4 h; Continuous load: 500 W | 277.77778 Ah |
| 100W for 8h | Required backup time: 8 h; Continuous load: 100 W | 111.11111 Ah |
| 500W for 8h | Required backup time: 8 h; Continuous load: 500 W | 555.55556 Ah |
| 100W for 12h | Required backup time: 12 h; Continuous load: 100 W | 166.66667 Ah |
| 500W for 12h | Required backup time: 12 h; Continuous load: 500 W | 833.33333 Ah |
| 100W for 24h | Required backup time: 24 h; Continuous load: 100 W | 333.33333 Ah |
| 500W for 24h | Required backup time: 24 h; Continuous load: 500 W | 1,666.66667 Ah |
Unchanged inputs: Nominal battery voltage = 12 V; Continuous load = 100 W; Required backup time = 8 h; Usable capacity fraction = 80 %; Conversion efficiency = 90 %; Extra design margin = 20 %. Rows change only the listed inputs. Values are arithmetic examples, not manufacturer performance claims.
Common questions
Is the extra margin a code requirement?
No. It is a user-selected planning allowance, separate from any manufacturer or locally required factor.
How should I use the result?
Capacity sizing does not check surge power, maximum battery current, charger compatibility or installation rules. Select equipment that satisfies those requirements separately.
How do I calculate the battery size needed for 8 hours of backup?
Multiply average load watts by 8, then divide by the usable fraction and efficiency. Include a separate, explicitly chosen margin if needed. Convert the resulting nominal Wh to Ah at the intended bank voltage.
How much battery capacity is needed for a whole house?
There is no universal house-size-to-battery formula. Enter an energy budget for the appliances that must run during the outage. Check motor starting demand and maximum battery power as well as total kWh.
Is a 20% battery sizing margin mandatory?
No. It is an illustrative input in this calculator. A project specification or manufacturer may require a different margin, aging allowance or temperature correction.
Does this perform IEEE 485 or IEEE 1115 battery sizing?
No. A standards-based design requires the appropriate edition, battery chemistry, duty-cycle segments, manufacturer discharge data and applicable correction factors. A constant-load energy estimate should not be labeled an IEEE-compliant result.
Can I size a substation or ship battery with this formula?
Only as a preliminary energy check. Protection, duty cycles, redundancy, charger recovery and applicable marine or substation requirements require a dedicated engineering calculation.
Is there a battery sizing calculation PDF or Excel sheet here?
The formula, assumptions and computed examples are readable on the page and can be printed. No downloadable official PDF, Excel workbook or IEEE worksheet is supplied. For a simple sheet, use required Ah = load_W*hours*(1+margin)/(volts*usable_fraction*efficiency).
Can I use Amara Raja, HBL, C&D or Franklin battery sizing data?
Enter verified ratings from the exact product and check manufacturer discharge specifications. This generic sizing page does not include those brands product databases or reproduce their approved sizing software.
Related calculators
Sources and formula basis
Source addresses are shown as plain text. Algebraic rearrangements, example tables and user-selected loss factors are calculated on this site. A reference does not endorse every illustrative input.
- FAA — watt-hour rating: nominal volts × amp-hourshttps://www.faa.gov/hazmat/packsafe/airline-passengers-and-batteries
- Cadex Battery University BU-503 — power, energy and timehttps://www.batteryuniversity.com/article/bu-503-determining-power-deliver-by-the-ragone-plot
Source pages checked: November 19, 2026. Verify current product data and locally adopted requirements before design or installation.