The method
Formula and calculation steps
Runtime = V × Ah × usable fraction ÷ (AC load W ÷ efficiency + DC idle W)
The battery supplies both converted AC power and a separate battery-side idle load. Use the DC bus voltage of the complete series string and the Ah of the parallel bank.
Not an APC, Eaton, CyberPower or Vertiv product runtime curve. Use manufacturer discharge curves for a purchase or critical backup requirement. VA alone does not give the real load watts.
UPS battery backup calculation and inverter autonomy
A UPS battery backup time calculation uses the DC battery bank energy, the real AC load in watts, conversion efficiency and standby consumption. Enter the complete string voltage and bank Ah. A 3 phase UPS battery backup calculation follows the same stored-energy balance when total real three-phase load watts are already known; phase configuration does not multiply the stored battery energy.
An inverter battery run time calculator must distinguish its battery-side no-load loss from AC appliance watts. The form treats idle watts as a separate DC loss. If your measured DC draw already includes all inverter losses, use the battery-life-by-amp-draw tool instead. Apparent power in VA is not automatically equal to watts.
Continue with: Battery Watt Hour Calculator · Battery Runtime Calculator
Worked example
A transparent starting point
12 V × 100 Ah × 80% ÷ (100 W ÷ 0.90 + 10 W) = 7.93 hours.
The values below are computed with the same formula as the calculator. They are examples, not manufacturer performance claims.
How one input changes the answer
| Continuous load (W) | Estimated UPS runtime |
|---|---|
| 50 W | 14.64407 hours |
| 100 W | 7.926606 hours |
| 150 W | 5.433962 hours |
All other inputs use the illustrative defaults in the form.
UPS battery backup calculation and inverter autonomy — calculated examples
Each row below is calculated from the stated case inputs. Inputs not changed in a row use the assumptions listed after the table.
| Case | Changed inputs | Result |
|---|---|---|
| 12V 100Ah bank, 100W AC | Nominal battery voltage: 12 V; Rated battery capacity: 100 Ah; Continuous load: 100 W | 7.92661 hours |
| 12V 100Ah bank, 300W AC | Nominal battery voltage: 12 V; Rated battery capacity: 100 Ah; Continuous load: 300 W | 2.79612 hours |
| 12V 100Ah bank, 500W AC | Nominal battery voltage: 12 V; Rated battery capacity: 100 Ah; Continuous load: 500 W | 1.69745 hours |
| 24V 100Ah bank, 100W AC | Nominal battery voltage: 24 V; Rated battery capacity: 100 Ah; Continuous load: 100 W | 15.85321 hours |
| 24V 100Ah bank, 300W AC | Nominal battery voltage: 24 V; Rated battery capacity: 100 Ah; Continuous load: 300 W | 5.59223 hours |
| 24V 100Ah bank, 500W AC | Nominal battery voltage: 24 V; Rated battery capacity: 100 Ah; Continuous load: 500 W | 3.39489 hours |
| 48V 100Ah bank, 100W AC | Nominal battery voltage: 48 V; Rated battery capacity: 100 Ah; Continuous load: 100 W | 31.70642 hours |
| 48V 100Ah bank, 300W AC | Nominal battery voltage: 48 V; Rated battery capacity: 100 Ah; Continuous load: 300 W | 11.18447 hours |
| 48V 100Ah bank, 500W AC | Nominal battery voltage: 48 V; Rated battery capacity: 100 Ah; Continuous load: 500 W | 6.78978 hours |
Unchanged inputs: Nominal battery voltage = 12 V; Rated battery capacity = 100 Ah; Continuous load = 100 W; Usable capacity fraction = 80 %; Conversion efficiency = 90 %; Battery-side idle consumption = 10 W. Rows change only the listed inputs. Values are arithmetic examples, not manufacturer performance claims.
Common questions
Do series batteries add amp-hours?
No. Four equal 12 V 100 Ah batteries in series are 48 V 100 Ah, not 48 V 400 Ah.
How should I use the result?
Not an APC, Eaton, CyberPower or Vertiv product runtime curve. Use manufacturer discharge curves for a purchase or critical backup requirement. VA alone does not give the real load watts.
Can this replace an APC, Eaton, CyberPower or Vertiv UPS runtime calculator?
No. Those products can have different cutoff thresholds, inverter loss curves and battery discharge behavior. This page provides a generic estimate; use the exact manufacturer model runtime chart for a rated backup duration.
How do I calculate UPS runtime by load?
Use the load total in real watts. Divide usable battery Wh by AC watts divided by efficiency plus separate battery-side idle watts. The example table compares loads while keeping the bank and loss assumptions explicit.
How do I calculate battery bank capacity for UPS?
For identical batteries, series changes voltage and parallel changes Ah. Four 12 V 100 Ah units in series form 48 V 100 Ah, containing 4,800 Wh nominally. Use the pack calculator to check the configuration.
Can I use a UPS battery sizing calculation spreadsheet?
The displayed formula can be reproduced in Excel with named cells for bank volts, Ah, usable fraction, AC watts, efficiency and idle watts. A spreadsheet using the same model is still a generic estimate, not a product certification.
Is this also an IPS or home inverter backup calculator?
It can estimate a steady load for those systems when bank voltage, capacity and losses are known. Check surge capability, battery current and low-voltage cutoff separately.
Related calculators
Sources and formula basis
Source addresses are shown as plain text. Algebraic rearrangements, example tables and user-selected loss factors are calculated on this site. A reference does not endorse every illustrative input.
- FAA — watt-hour rating: nominal volts × amp-hourshttps://www.faa.gov/hazmat/packsafe/airline-passengers-and-batteries
- Cadex Battery University BU-503 — power, energy and timehttps://www.batteryuniversity.com/article/bu-503-determining-power-deliver-by-the-ragone-plot
- Cadex Battery University BU-302 — series and parallel configurationshttps://www.batteryuniversity.com/article/bu-302-series-and-parallel-battery-configurations
Source pages checked: November 19, 2026. Verify current product data and locally adopted requirements before design or installation.